Re: Quantity Changes in CJ20N not updated in PR

$
0
0

Hi Virendra,

 

I replicated the scenario in the following steps,

 

1) Created a PR from project for 4 quantity

2) Created a PO wrt this PR for 4 quantity

3) Did the GR for 3 quantity

4) Then changed the quantity in CJ20N for the material to 3 and saved the project.

5) Checked the PR in ME53N and PR quantity changed to 3.

6) In ME22N changed the PO quantity from 4 to 3

7) Checked CJI5 and i cant see any remaining commitment.

 

It worked ok for me. Hope this is what you did.

 

Regards,

Gokul