Hi Experts,
We have an issue with Approve PO Apps.
The release strategy is getting deleted while approving at the final level.
i.e, if there are 4 levels, Fiori app works fine with all 3 levels. At 4th (final) level, app shows "Purchase order is approved" and clears from fiori list.
When go back and check in ECC backend, the release strategy is missing. This is getting deleted.
The functionality in backend works proper without any issue. The issue is only when final release is done through Fiori. all the previous levels works fine with Fiori app.
In case of Approve PR, this issue is not there. After the final level, PR release strategy remains.
Can anybody help?
Screenshot change document after final PO release (from fiori) is as below:
the release strategy has gone blank here.
Thanks,
Prem